Oct 032014
 

A Project Status Meeting regarding the Main Street Bridge replacement project in Deer Lodge will be held on Thursday October 9, 2014 at the Elks Lodge at 230 Main Street, from 2 pm.

This meeting is convened by Bauer & Buck Construction of Missoula.

Jul 252014
 

Press release from the City of Deer Lodge;

** PLEASE NOTE ** All residents located in the water main replacement project area – WATER will be turned Off on July 29, 30, 31 and Aug 1, 2014

The roughly 100 residents/businesses located only in the following areas off of Main Street will be affected:

1) Cottonwood Ave (west side) – only on north side of the road (ex: Elks bldg/NAPA store) to Railroad Tracks.

2) All of California Ave on the west side of Main Street

3) All of Rainbow Ave on the west side of Main Street

4) Second St. from NAPA to Rainbow Ave

5) The entire West Side of Main Street from Cottonwood to the Grant-Kohrs Ranch

All effort will be made to have the water back on for the evening hours.

The City sincerely apologizes for the inconvenience.

If you have any questions, call Mark of Bauer and Buck Construction at 406-880-5473

Jul 232014
 

The following message has been received from Bauer and Buck Construction:

All environmental permits are now in place for the Main Street Bridge Project and work will commence on Monday, July 28, 2014, 7:00 am with the placement of the detour.

We also received the following release from the City of Deer Lodge:

Due to the Main Street Bridge Project, the water main and all water services connected to that Main will be turned off on July 29, 30, 31 and August 1, 2014. All effort will be made to have the water back on for the evening hours. The City sincerely apologizes for the inconvenience.

(Added on July 25th: The water shut off will be from approx. 7 am till 7 pm from Tuesday through Friday, affecting the west side of Main Street from City Hall north to Grant-Kohrs Ranch. )

Please direct any inquiries to Mark of Bauer and Buck Construction at 406-880-5473

Jul 032014
 

The following message has just been received by the Powell County Chamber of Commerce regarding the Main Street Bridge Construction Project in Deer Lodge:

The notice to proceed date has been postponed until further notice from Scott Cunningham, P.M., MDT. We will not begin work on Monday, July 7.

I will keep you informed.

Thank you,

Stacey Otte
Office Manager
406.830.6152

Mark Buck Construction, Inc.
DBA Bauer and Buck Construction
 

Jun 232014
 

A Community Information Meeting regarding the Construction Project for Main Street Bridge in Deer Lodge will be held on Wednesday June 25, 2014 at the Elks Lodge at 230 Main Street, from 2 till 3 pm.

The Project is due to commence on TBA, and this meeting will be your chance to hear from the contractors, Bauer & Buck Construction of Missoula.